Fleming Elevator Updates (8-3-2016)
8-3-2016
- The Fleming elevator project is complete. Elevator has been inspected and has passed inspection of all components and load test. The elevator is in operation.
 
7-25-2016
- New jack has been delivered at ETS, July 25
 - ETS will deliver the jack to Fleming first thing in the morning, July 26
 - Updated anticipated completion date and elevator operational, July 29
 
7-19-2016
- New jack and piston have been shipped from California, July 18
 - ETS beginning work on elevator repair, July 20
 
7-13-2016
- ETS crew will be on site to finish the demolition and make ready the elevator well to accommodate the new jack, July 20
 
7-5-2016
- New jack and plunger shipping from California, July 15
 - ETS (Elevator Transportation Services, Inc.) crew starting tear down in preparation for new jack and plunger installation, July 18
 - New jack and plunger estimated to arrive in Houston, July 21
 - Anticipate elevator being operational, July 25
 
6-1-2016
- Original outage submitted