Wi-Fi Upgrades in Academic and Research Areas (Project UIT16919)
Overall Project Status: In Progress
Project Goals & Objectives
- Meet or exceed our SLA of minimum 5Mbps in all academic and research areas
- Upgrade Wi-Fi access points and cover rooms at capacity in all academic and research areas
Scope of Work
- Buildings: Science and Research 1, Science and Research 2, Fleming, Health and Biomedical Sciences, Science and Teaching Lab, SERC, SEC, PGH, and Garrison (CASA)
- Upgrade of 170 existing access points to 802.11n, move them below the ceiling to meet current design standards, and install 165 additional access points
Major Milestones
ACTIVITY | START | END | NOTES |
---|---|---|---|
SR1 550 | 6/1/16 | 6/29/16 | SR1 will be substantially completed on Wednesday 6/29 |
Fleming 564 | 6/1/16 | 6/30/16 | Fleming will be substantially completed on Thursday 6/30 |
SR2 551 | 6/4/16 | 6/30/16 | SR2 will be substantially completed on Thursday 6/30 |
Garrison 532 | 6/4/16 | 6/29/16 | Garrison will be substantially completed on Wednesday 6/29 |
HSC 593 | 6/5/16 | 6/29/16 | HSC will be substantially completed on Wednesday 6/29 |
PGH 547 | 6/6/16 | 7/1/16 | PGH will be substantially completed on Friday 6/31 |
SEC 545 | 6/20/16 | 7/1/16 | SEC will be substantially completed on Friday 7/01. |
SERC 545 | 6/7/16 | 7/12/16 | SERC will be substantially completed on Friday 7/12 |
STL | 6/8/16 | 7/12/16 | STL will be substantially completed on Wednesday 7/12 i |
All Buildings | 7/13/16 | 8/9/16 | QA and configurations in all buildings |
Project End | 8/10/16 | Project will be substantially completed on Wednesday 8/10 |